Sophie2020-06-30 17:45:14
同学你好
以下是原版书的原话
“The initial cuts typically occur in orders for technology and light equipment because there are shorter lead times from order to delivery and managers may simply not place any additional orders. It often takes longer to cancel or halt construction activity or the installation of larger, more complex pieces of equipment, and cutbacks in these areas unfold with a longer lag.”
所以construction activity cancel 起来是比较慢的,所以不符合题目quickly
在衰退期,企业的设备的使用会减少很多,所以会减少维护降低成本